10
10: The lower level horizontal beams for the L&N's
north Decoursey staging yard. The plywood decking
to the right is the L&N's south Atlanta staging and the
Southern's South Citico staging.
floor using wedge anchors. I had 2”x2” aluminum angles made
for the framework corners. I did need to have the horizontal
members welded later on. A slight bow in the ¾’ inch plywood
deck moved the horizontal members out of position.
1×3 pine was attached to the horizontal members using self
tapping drywall screws in a 1/8” hole for the risers. One bonus
I had was turning in the scrap aluminum to a salvage yard for
money. Try that with scrap lumber!
The helix’s roadbed is made with 1/8” door skin plywood. This
was cut to the proper width and radius in different lengths.
The length was determined by the position of the different
arcs on the door skin sheet. These pieces were then laminated
together with contact cement.
The risers are made from ¾” furniture grade pinewood. I cut
dadoes at 4” intervals, then ripped the boards into ¾” strips to
accept the helix roadbed. The track was glued to the roadbed
contents